Cabras #4 Power Plant Repairs

Project Details

TUTOR PERINI AFFILIATES

Black Construction Company
Prime Contractor
Contract Amount: $2.44 Million

OWNER
Guam Power Authority

LOCATION
Piti, Guam

COMPLETION
2001

Project Description

This project was awarded to Black Construction Corporation to replace and restore equipment and facilities damaged by a fire at the GPA Cabras No. 4, 40-megawatt baseload generator. As a result of GPA’s demand for a reserve baseload generator, the contract required the completion of all work within 120 calendar days from the Notice to Proceed.

Awards

Guam Contractors Association 2001 -Mechanical-Industrial Category