Division 20 Portal Widening & Turnback Facility Project

Project Details

TUTOR PERINI AFFILIATES

Tutor Perini
Prime Contractor
Contract Amount: $549 Million

Fisk Electric Company
Electrical Subcontractor
Contract Amount: $176 Million

Becho, Inc.
Specialty Subcontractor
Contract Amount: $6 Million

Desert Mechanical Inc.
Mechanical Subcontractor
Contract Amount: $350,000

OWNER
Los Angeles County Metropolitan Transportation Authority

LOCATION
Los Angeles, CA

ARCHITECT
T.Y. Lin International

SIZE
16 Miles

COMPLETION
2025

Project Description

The Division 20 Portal Widening Turnback (Division 20) project will provide widening of the existing portal for the Metro Red and Purple Lines Maintenance Yard (Division 20 Rail Yard), development of a high-capacity turnback facility, an increase of train storage capacity, and a reconfiguration of existing internal tracks and access roads. The Project is located within the vicinity of the existing Division 20 Rail Yard. The Project is generally bounded by the BNSF ROW to the east, Santa Fe Avenue and Center Street to the west, Commercial Street to the north, and 6th Street Bridge to the south. 

The project work includes (but is not limited to):

  • Demolition
  • Civil improvements
  • Center street improvements
  • Trackwork
  • New northern and southern storage yards
  • Turnback facility
  • Utility protection and relocation
  • Structures
  • 1st street viaduct improvements
  • Systems infrastructure and systems integration