Market
Rehabilitation of Five Electrical Substations in Haiti
Project Details
TUTOR PERINI AFFILIATES
Perini Management Services, Inc.
Prime Contractor
Contract Amount: $14.91 Million
Fisk Electric Company
Electrical Contractor
Contract Amount: $1.8 Million
OWNER
U.S. Agency for International Development
LOCATION
Port-au-Prince, Haiti
ARCHITECT
AECOM and PG&D Engineers
COMPLETION
2013
Project Description
Rehabilitation of five electrical substations in Port-au-Prince, Haiti, following the 2010 earthquake, including testing existing equipment, procuring five transformers, and relocating eight others that were already owned by the Haiti electrical utility. The work also included repairs to perimeter fencing and substation buildings and installation of SCADA systems. A stringent safety training program was implemented for the local unskilled laborers that resulted in zero safety incidents.
Awards
Government Performance Evaluation - Exceptional Quality & Management
“Perini has exceeded our expectations as far as design and construction, and have truly set the standard for electrical work in Haiti.”Government Performance Evaluation