East Side Access CQ033

Mid Day Storage Yard

Project Details

TUTOR PERINI AFFILIATES

Tutor Perini Civil
Prime Contractor
Contract Amount: $292 Million

Five Star Electric
Electrical Subcontractor
Contract Amount: $117 Million

OWNER
NYC Metropolitan Transportation Authority

LOCATION
New York, NY

ARCHITECT
GEC (PB/STV/Parsons)

SIZE
9 Miles of Track

COMPLETION
2021

Project Description

This portion of the East Side Access project is for the construction of a storage yard facility for commuter railcars. The work will be performed primarily within the Sunnyside Yard and Harold Interlocking area in Queens, New York, and will include track beds and access roads, over 100 utility structures, nine miles of track, 61,000 linear feet of mechanical piping, 552,000 linear feet of conduit, 1,039,000 linear feet of wire and cable, 86 switches, three traction power substations, 256 poles, and personnel access bridge.

 

RELATED PROJECTS
ESA CH053 (Harold Structures Part 1)
ESA CH054A (Harold Structures Part 2)
ESA CH057 (Harold Structures Part 3)
ESA CH061A (Michaels – Track A Cut & Cover Structures)
ESA CM005 (Manhattan South Structures)
ESA CM006 (Manhattan North Structures)
ESA CM007 (Grand Central Terminal Caverns)
ESA CM014B (Grand Central Terminal Concourse Facility and Fit-Out)
ESA CQ031 (Queens Bored Tunnels)

ESA CQ032 (Queens Structures and Plaza Substation)
ESA CS086 (Systems Package No. 3)
ESA CS179 (Systems Facilities Package No. 1)

Photo Credits: Bernstein Associates